Our MOs are no longer scheduling based on Item Mfg lead-time. For example, if I enter a MO with Backward Infinite scheduling for a Make Item that has a 25 day lead-time, the MO makes my Start Date the same as my Due Date. What's worse (and possibly related) our Request Resolution is sporadically suggesting us to buy Items that go into Makes even though no MO has been created for the Makes (though the makes are backordered). Do we have major low level issues in the system? What could be the fix?
↧